The Office of the Municipal Planning & Development Coordinator has been implementing programs and projects for the 1st Quarter of Fiscal Year 2008 January to April Period. So as to institutionalize and monitor what these programs and projects are, we are submitting this 1st Quarterly Report.

This is also designed for your information and guidance.


CRISLYNNE MAE A. SUGIAN-HUERTA, MPA
MPDC
 

Rationale:

The Office of the Municipal Planning & Development Coordinator is mandated by the Civil Service Commission to formulate developmental plans of the municipality as well as provide technical assistance to the barangay planners and other organizations for the formulation of local plans such as barangay development plan and others for inclusion to the higher plans in the municipality.

Thus, for the 1st Quarter of 2008 January to April Period different activities had been spearheaded by the office for the implementation of plans and programs in the Local Government Unit.

Technical Assistance had been given by the personnel & staff of the office to different institutions and organizations so as to come up with their developmental plans. All 14 barangays of the municipality had undergo training of barangay development planning attended by the Barangay Planners composed of the Barangay Captain, Brgy. Secretary, Treasurer and one Brgy. Kagawad. After the Trainor’s Training conducted, there are already 10 barangays visited by the Municipal Planning Team and assisted in formulating their 5-Year Developmental Plan. Visitation to the 4 remaining barangays is now on going.

The Office is also spearheading the Community Based Monitoring System (CBMS) wherein 10 Enumerators had been trained before sending them to the field. There are 7 barangays who had been surveyed. Results of the survey are now being reviewed for encoding to the CBMS System to be provided for free by the Provincial Government.

Other special projects managed by the Office has also been given preferential attention and focus specially in the monitoring and evaluation of the DAR-IFAD PAF sub-projects. Details of the report are provided in the next pages.

In totality, it has been a busy quarter in the Office of the Municipal Planning & Development Office. Its objectives had been accomplished and will continue to work for the next quarter to achieve better performance.

Objectives:

1. To be able to assist and formulate fourteen (14) 5-Yr. Comprehensive Barangay Development Plan2. To assist the Barangays in the conduct of their Barangay Assembly
3. To gather data in all 14 barangays for Community Based Monitoring System to improve data banking
4. To institutionalize people’s organizations for effective implementation of alternative livelihood programs.